On To the Vertical Stabilizer
Nov 20,2019
As with the HS, the VS will be assembled with clecoes before the dimpling is completed. The step seen here is the doubler being attached to the rear spar.
Nov 20,2019
As with the HS, the VS will be assembled with clecoes before the dimpling is completed. The step seen here is the doubler being attached to the rear spar.
Nov 10, 2019
To rivet the HS you will need to remove the rear spar to be able to buck the rivets.
Nov 9, 2019
Shown with the rear spar attached and ready for rivets.
Nov 8, 2019
Before the final fit the spars, ribs, and skins all need to be dimpled. Be sure to use the correct size dimpler before starting.
Nov 7,2019
With the ribs in place this is my first try at fitting the skins. Important to declare left and right at this point. Also, we taped the holes that we are not going to work with at this particular time.
Nov 7, 2019
Time to add the ribs to the horizontal stabilizer.
Nov 17, 2019
Beginning construction on front spar for the second time.
Nov 7, 2019 8hrs
Got the new parts in and I am having a lot more success with the rivet installation. Following are a few pictures which exhibit the improvement.
Oct 15,2019 9 hrs
This required ordering new parts and completing the tool box exercise. This taught me to know the correct rivet size and most of all how to properly drill out damaged rivets.
Oct 15,2019 8hrs
As well as the riveting went on the rear spar, not so good on the front spar.
Oct 10,2019 9 hrs
This pic shows the work on the rear spar for the horizontal stabilizer.
Oct 9,2019 9hrs
Inventoried both kits.
Oct 8,2019 10 hrs
The kits were delivered in less than acceptable condition.